January 11, 2021Experience start
-
January 30, 2021Sprint 1
-
February 27, 2021Sprint 2
-
April 1, 2021Sprint 3
-
April 30, 2021Final Submission
-
May 1, 2021Experience end
Timeline
-
January 11, 2021Experience start
-
January 30, 2021Sprint 1
Needs assessment and project charter.
-
February 27, 2021Sprint 2
Virtually provide the client with a comprehensive solution. Be prepared to implement that solution.
-
April 1, 2021Sprint 3
Change control. Based on the feedback from the client on Milestone 2, what changes need to be made to the infrastructure? There may be implementation work, training, or research as well.
-
April 30, 2021Final Submission
Close Project. All activities should be completed. The Teams will present the final results to the client and instructor.
-
May 1, 2021Experience end
Categories
Information technology Operations Project managementSkills
active directory administration information technology and business analysis information technology security windows server operations networking & information systemsIs your organization looking for a junior Information Technology Systems technician?
Students in this project course focus on gaining experience in some aspect of networking, Windows administration, helpdesk support, IT project participation, and more.
Learners will gain practical experience by assisting you in planning, developing, administration, and customer support.
These students may be available for internship after the project is complete.
The learners will follow a structured project guideline as mentioned in the milestones section and will deliver the final project code with a final written report. Learners are also expected to present their work based on their final report.
Project timeline
-
January 11, 2021Experience start
-
January 30, 2021Sprint 1
-
February 27, 2021Sprint 2
-
April 1, 2021Sprint 3
-
April 30, 2021Final Submission
-
May 1, 2021Experience end
Timeline
-
January 11, 2021Experience start
-
January 30, 2021Sprint 1
Needs assessment and project charter.
-
February 27, 2021Sprint 2
Virtually provide the client with a comprehensive solution. Be prepared to implement that solution.
-
April 1, 2021Sprint 3
Change control. Based on the feedback from the client on Milestone 2, what changes need to be made to the infrastructure? There may be implementation work, training, or research as well.
-
April 30, 2021Final Submission
Close Project. All activities should be completed. The Teams will present the final results to the client and instructor.
-
May 1, 2021Experience end
Project Examples
These student are capable any of the following roles:
- Junior IT Tech
- Junior Service Desk Analyst
- Help Desk Analyst
- Junior IT Support Analyst
- IT Support Analyst
- Desktop Support
- Technical Support
- Customer Support Representative
- PC Technical Support
- Network Administrations
- Internet Resource Management
- Information Systems Project Manager
- Business and Systems Analyst
- Computer Service Technician
- IT Support Specialist
- Information Systems Analyst
Companies must answer the following questions to submit a match request to this experience:
Please have some details regarding workload and time frames.
Be available for a quick phone call with the instructor to initiate your relationship and confirm your scope is an appropriate fit for the course.
Please provide your current IT state or setup.
Provide a dedicated contact who is available to answer periodic emails or phone calls over the duration of the project to address students' questions.
Timeline
-
January 11, 2021Experience start
-
January 30, 2021Sprint 1
-
February 27, 2021Sprint 2
-
April 1, 2021Sprint 3
-
April 30, 2021Final Submission
-
May 1, 2021Experience end
Timeline
-
January 11, 2021Experience start
-
January 30, 2021Sprint 1
Needs assessment and project charter.
-
February 27, 2021Sprint 2
Virtually provide the client with a comprehensive solution. Be prepared to implement that solution.
-
April 1, 2021Sprint 3
Change control. Based on the feedback from the client on Milestone 2, what changes need to be made to the infrastructure? There may be implementation work, training, or research as well.
-
April 30, 2021Final Submission
Close Project. All activities should be completed. The Teams will present the final results to the client and instructor.
-